Providing safe and reliable electrical service to our customers is El Paso Electric's number one priority.

Joint Use and Pole Attachments

El Paso Electric Company-owned distribution poles can be made available for wireline and wireless pole attachments, provided that all carriers and providers have a fully executed pole license agreement with 明升ms88平台. If your company wishes to enter into a pole attachment agreement with 明升ms88平台, please contact 明升ms88平台’s Joint Use team (contact information below) to request an agreement.

This website contains information regarding 明升ms88平台’s current pole attachment policies and procedures. 明升ms88平台 updates this website from time to time, so please check back to ensure you have 明升ms88平台’s latest policies, documents, and contact information. 

Click here to view 明升ms88平台's service area

Contact Us

Please direct any questions to 明升ms88平台 Joint Use at (915) 543-2232 or by email to JointUse@megschomp.com

SpidaMIN

明升ms88平台 requires that all Licensees use SpidaMIN, a web-based asset management system, to communicate with 明升ms88平台 regarding pole attachments. 明升ms88平台 primarily utilizes SpidaMIN for Pole Permit Applications, Overlash Notices, and Transfer Notices. Upon request, the 明升ms88平台 Joint Use team will provide login credentials to licensees and/or contractors working on behalf of licensees.


Certificates of Insurance

明升ms88平台’s standard pole license agreement contains insurance requirements for all licensees. Certificates of Insurance for licensees must be emailed to JointUse@megschomp.com on or before the expiration date of the current certificate.


Overlash Notification

明升ms88平台 requires a 15-day advanced notice of overlash using the Overlash Notification workflow in SpidaMIN. If 明升ms88平台 determines based upon its engineering analysis that the proposed overlashing cannot proceed because it would create a capacity, safety, reliability, and/or engineering issue, or if make-ready is required prior to overlashing, 明升ms88平台 will provide the licensee with notice of same and supporting documentation within the 15-day period.


Application Process

Pole Attachment applications are required if:

  • Attaching one (1) or more new wireline pole attachments
  • Attaching one (1) or more new wireless pole attachments
  • Modifications (any change in type, nature, dimensions, weight, or location of an existing pole attachment)

For each application submitted, 明升ms88平台 will either approve the application, conditionally approve the application contingent upon completion of necessary make-ready work, or deny the application for reasons of safety, reliability, capacity and/or generally applicable engineering purposes.

Requirements of Pole Attachment Applications

  • OTMR (for simple make ready in the communications space)

Licensees may utilize the OTMR process for “simple make-ready” in the communications space, meaning make-ready where the existing attachments in the communications space on the pole can be transferred without any reasonable expectation of a service outage or facility damage and where the make-ready does not require splicing of any existing communication attachment or relocation of any existing wireless equipment. 

The OTMR process is not available for jobs that will require power space make-ready, pole change-outs, or jobs that involve “complex make-ready.”  “Complex make-ready” includes transfers and work within the communications space that would be reasonably likely to cause a service outage or facility damage, such as splicing of any communication attachment or relocation of existing wireless attachments. Any and all wireless activities, including those involving mobile, fixed, and point-to-point wireless communications and wireless internet service providers, are “complex make-ready.” 

The licensee must provide three (3) business days’ notice to 明升ms88平台 prior to performing the OTMR survey. Following performance of the survey, the licensee (or applicant on behalf of the licensee) must submit an application to 明升ms88平台 via the SpidaMIN OTMR Pole Permit Application workflow with the construction plans uploaded into the SpidaMIN project as one .pdf attachment. The application must meet the following specified criteria--otherwise the application will be deemed incomplete:

Access the OTMR Pole Attachment Application Requirements here.

  • Non-OTMR (including complex make ready and make-ready above the communications space)

Licensee (or applicant on behalf of the licensee) must submit an application to 明升ms88平台 via the SpidaMIN Non-OTMR Pole Permit Application workflow with the construction plans uploaded into the SpidaMIN project as one .pdf attachment. The application must meet the following specified criteria--otherwise the application will be deemed incomplete:

Access the Non-OTMR Pole Attachment Application Requirements here.

Strand Mounted Wireless Equipment

Licensees wishing to install strand mounted wireless equipment must follow the protocol set forth in the Strand Mounted Wireless Equipment workflow in SpidaMIN.


Additional Contact Information

Line Extension Phone Numbers
(915) 351-4224 - Texas
(575) 523-3620 - New Mexico

Line Extension Tracker

Trouble and Power Outages
(915) 877-3400 - Texas
(575) 523-7591 - New Mexico

Customer Care
Texas: (915) 543-5970
New Mexico: (575) 526-5555

明升ms88平台 Chat